The construction of the project has been completed with the final installation of the pavers in the Wishbone and Overlook areas immediately adjacent to the Dupont Circle. The PaveGen Pavers and the remaining London Pavers have been installed. The bike racks, granite benches, and landscaping are also completed. Since the ribbon cutting ceremony has already taken place, the Overlook area is now open to public.

Report: November 7, 2016


Completed PaveGen and London Pavers were installed in the Wishbone Island.

Completed PaveGen Pavers in Overlook. Granite benches were also installed.